A pre-engineered metal building (PEMB) moves fast once the order is placed. The design, approval and detailing stages decide whether it keeps moving: a missing anchor bolt reaction or an unclear framed opening can hold up fabrication for days. This checklist sets out what a complete PEMB design and detailing package should contain, stage by stage, and what to check before anything goes to the shop.
Stage 1: Design basis and loads
Everything downstream depends on agreeing the design criteria first. The design basis records the building geometry and every load and limit the design will use, so the owner, the engineer of record and the manufacturer are working from the same numbers.
- Building geometry: width, length, eave height, roof slope, bay spacing, frame type (clear span, multi-span, lean-to) and end-wall framing.
- Governing codes: IBC, ASCE 7, AISC 360 and AISI S100 with MBMA guidance for US projects; IS 800, IS 875 and IS 1893 for projects in India.
- Dead, collateral and live loads, roof snow (including drift at steps and parapets), wind and seismic parameters, and risk category.
- Crane data: capacity, span, wheel loads and service class for any top-running, under-hung or monorail cranes.
- Serviceability limits for frame drift and member deflection, chosen to suit the wall and roof materials.
- Special loads: mezzanines, rooftop units, solar panels, hung sprinklers and future expansion.
Deliverable: a design basis report that the client approves before analysis starts.
Stage 2: Analysis and design calculations
PEMB software such as MBS designs the primary rigid frames as tapered built-up members, then sizes the secondary framing and bracing. A complete calculation package covers:
- Primary frames: member sizes, connection forces and checks for every load combination.
- Secondary members: cold-formed purlins and girts, including lap and bracing assumptions.
- Lateral systems: rod, cable or portal bracing and the diaphragm path.
- Crane runway beams, brackets and stops where cranes are present.
- Column base reactions for every load case, which the foundation engineer needs.
- A weight comparison between the estimated and the final design weight, so cost surprises surface early.
Stage 3: Approval drawings
Approval drawings let the owner and engineer of record confirm the building before steel is cut. They are drawn to scale and normally include:
- Anchor bolt plan with bolt sizes, projections, setting dimensions and column reactions.
- Frame cross-sections with member sizes and key elevations.
- Roof and wall framing plans, including framed openings for doors, louvers and windows.
- Bracing layout, sheeting and trim details, and accessory locations.
Stage 4: Shop drawings, erection drawings and CNC files
Once approval comments are closed, detailing turns the design into everything the fabricator and erector need:
- Shop drawings for built-up members, plates and secondary parts, with a shipper (shipping list).
- Erection drawings with clear part marks, so every piece has one place in the building.
- Plasma/CNC and detailing base files for automated cutting.
- Checker files with red marks, kept with the job so every correction is traceable.
Checklist before you release for fabrication
- The loads in the final design match the approved design basis, including late changes to collateral or crane loads.
- Anchor bolt reactions have gone to the foundation engineer, and the foundation design has been checked against them.
- Frame drift and deflection limits suit the wall system (masonry and glazing need tighter limits than metal panels).
- Every framed opening is sized from the actual door or louver schedule, with jambs and headers designed for wind.
- Crane runway elevations, stops and clearances agree with the crane supplier's data.
- Accessory and equipment loads (HVAC, solar, sprinklers) are in the design, not just on the drawings.
- Every checker comment is closed, and the revision history is clear on each sheet.
How Structree handles PEMB packages
Our PEMB team designs and details clear-span, multi-span, multi-gable and hybrid buildings to AISC, MBMA, ASCE 7 and IBC, using MBS, Tekla and SDS2. Every drawing is checked by a separate checker, and each customer has a dedicated account manager. See our PEMB design and detailing services or request a quote.
Frequently asked questions
What is included in PEMB approval drawings?
Approval drawings normally include the anchor bolt plan with column reactions, frame cross-sections, roof and wall framing plans with framed openings, the bracing layout, and sheeting and trim details, all drawn to scale for owner and engineer review.
Which codes are PEMBs designed to?
In the USA, PEMBs are typically designed to the IBC, ASCE 7 loads, AISC 360 for hot-rolled and built-up steel and AISI S100 for cold-formed members, with MBMA guidance. In India, IS 800, IS 875 and IS 1893 are commonly used.
Why does the foundation engineer need the anchor bolt reactions early?
Foundations are usually built before steel arrives, so they are on the critical path. The column reactions, including horizontal thrust and uplift, decide footing size, anchor rod design and any tie rods.